Robeson Elementary School
2501 Southmoor
Champaign, IL
A geothermal system will accommodate this elementary school renovation. This project consists of 84 wells, 250’ deep for a total of 21,000’ drilled.
Westview Elementary School
703 S. Russell
Champaign, IL
As part of the renovation work at Westview, a geothermal system will be installed. This project consists of 90 wells, 250’ deep. Project completion is scheduled for summer 2010.
Thomas Jefferson Primary School
918 W Florence Ave
Peoria, IL
District 150 is in the process of renovating several schools. Geothermal heating and cooling is a part of the renovation for Thomas Jefferson Primary. The project consists of 168 wells, 300’ deep for a total of 50,400’ drilled. Drilling at the school started in May. We plan to complete the work in the summer.
Hines Primary School
4603 N Knoxville Avenue
Peoria, IL
As part of District 150’s school renovation projects Hines Primary will include a new geothermal heating and cooling system. The drilling portion of the project includes 100 wells, 300’ deep. We plan to begin working the middle of May.
Davis Center: Decatur Housing Authority
1808 E Locust
Decatur, IL
This project consists of 22 wells, 300’ deep. We plan to complete the project in late summer 2010.
Bottenfield Elementary School
1801 S Prospect
Champaign, IL
There will be 99 geothermal wells drilled at Bottenfiled elementary this summer. The wells will be 250’ deep. Project completion is scheduled for fall of 2010.